Spring Valley Dam Spillway Project
 
Posted on Friday May 17, 2019
 

Based on the tentative schedule provided by the contractor for the Spring Valley Dam Spillway Project the drawdown schedule has been revised.  The new tentative schedule is:

  • Closure of Memorial Causeway; early July (after 4th) - Memorial Causeway will be closed for the duration of the project

  • Lake drawdown to begin early August.  Drawdown will take approximately two weeks, weather dependent.

  • Projected duration for the project is 6 months
 
 